By Kamusime Banabasi
-Over 3 billion shillings have been
spent on government projects excluding roads in Kisoro district in the
financial year 2022/23, according to RDC Hajji Shafique Sekandi.
Sekandi revealed this on Thursday 15th
June 2023 while in his office after completing his district wise tour of
commissioning and handing over completed government projects to beneficiary
communities.
Among these projects include water
supply projects worth over 277 million shillings, institution infrastructure
like classroom blocks, VIP latrines, administration offices all worth over
1,227 million shillings and livestock and seed supplies worth 492 million
shillings.
RDC Sekandi commended Kisoro district
council and other leaders who have worked in unison to ensure that most of
these projects are a success.
Hajji Sekandi says that he has also
used his tour to monitor other unfinished government projects, sensitizing
locals about the parish development model and monitoring the progress of the
government in fulfilling NRM's 2021/26 manifesto program.
He noted that the district has greatly
improved in its operations, a reason why it was ranked number one in government
funds absorption for the last financial year and believes the same will happen
in this financial year.
Sekandi says that since he embarked on
regular monitoring of government projects last year, a number of contractors
have improved their quality of work. He called upon beneficiary communities to
always communicate abnormalities noticed during implementation of government
projects.
Meanwhile, his last tour was in sub
counties of Bukimbiri, Nyundo and Rubuguri town council where he commission a
25,000 litre tank at Mukungu village, 25,000 litre tank at Kayihimure
primary school in Bukimbiri, 12,000 litre tank at Rugandu primary school in
Rubuguri and a 2 classroom block at Gisoni primary school in Nyundo sub county.
RDC Sekandi noted that the government
is pushing to achieve its 2040 vision.
The table shows how money was spent on water supply projects
S/NO |
PROJECT |
LOCATION /SUB
COUNTY |
CONTRACT SUM |
REMARKS |
1 |
Completion
of Muyove gravity flow scheme in Kaburiga trading centre in Nyabwishenya sub
county |
Nyabwisshenya |
204,507,809 |
Commissioned
and functional in use |
2 |
Construction
of 25CM ferro cement rain water tank in Gatwe village Muramba s/c |
Muramba |
28,402,600 |
Commissioned
and functional in use |
3 |
Construction
of 25CM ferro cement rain water tank in Rusekye village Bukimbiri s/c |
Bukimbiri
|
28,469,506 |
Commissioned
and functional in use |
4 |
Construction
of 25CM ferro cement rain water tank in Gisasi village Kanaba s/c |
Kanaba |
28,472,220 |
Commissioned
and functional in use |
5 |
Construction
of 25CM ferro cement rain water tank in Buzeyi village Nyarusiza s/c |
Nyarusiza |
28,446,683 |
Commissioned
and functional in use |
6 |
Construction
of 25CM ferro cement rain water tank in Kanyabukngu village Nyakabande s/c |
Nyakabande |
28,345,016 |
Commissioned
and functional in use |
7 |
Construction
of 25CM ferro cement rain water tank in Murambi village Rwaramba s/c |
Rwaramba |
28,349,854 |
Commissioned
and functional in use |
8 |
Construction
of 25CM ferro cement rain water tank in Kibande village Muramba s/c |
Muramba |
28,193,740 |
Commissioned
and functional in use |
9 |
Construction
of 25CM ferro cement rain water tank in Ndago
village Nyarusiza s/c |
Nyarusiza |
28,449,682 |
Commissioned
and functional in use |
10 |
Construction
of 25CM ferro cement rain water tank in
Mukungu village Nyundo s/c |
Nyundo |
28,359,070 |
Commissioned
and functional in use |
11 |
Construction
of 25CM ferro cement rain water tank in Rwankoni village Chahi s/c |
Chahi |
28,349,854 |
Commissioned
and functional in use |
12 |
Construction
of 4 stance vip latrine at Kabami play ground |
Chahafi
Town Council |
22,999,380 |
Commissioned
and functional in use |
13 |
Construction
of 12CM ferro cement tank at Kabingo P/S |
Murora |
10,072,834 |
Commissioned
and functional in use |
14 |
Construction
of 12CM ferro cement tank at Kagera P/S |
Nyakabande |
9,974,248 |
Commissioned
and functional in use |
15 |
Construction
of 12CM ferro cement tank at Rugandu P/S |
Rubuguri
Town council |
10,188,242 |
Commissioned
and functional in use |
16 |
Construction
of 12CM ferro cement tank at
Busamba P/S |
Chahi |
10,058,792 |
Commissioned
and functional in use |
17 |
Construction
of 12CM ferro cement tank at Kaburasazi P/S |
Busanza |
10,064,456 |
To
be commissioned when there is water in
a tank |
18 |
Construction
of 12CM ferro cement tank at Kateriteri
P/S |
Bukimbiri |
10,115,196 |
Commissioned
and functional in use |
19 |
Protection
of Kazabwayera spring |
Kirundo |
4,439,160 |
Commissioned
and functional in use |
20 |
Rehabilitation
of Gatare Gravity Flow Scheme in Nyarubuye sub county |
Nyarubuye |
58,829,144 |
Commissioned
and functional in use |
|
Total |
|
635,087,486 |
|